  • Space ribs out evenly on top of slab on 2 layers of DPC (damp course) with a block in between the ribs for accurate spacing.
  • Install the support shuttering and props to support slab underneath crossribs / stiffner ribs @ equal centers of 1.5m (leveled).
  • Place the balance of the blocks as per engineer’s drawings. No blocks to be placed on top of crossribs.
  • Place the Y-10 steelbar reinforcing on top of crossrib shuttering.
  • Install all beams-, skylights- and cantilever reinforcing as per engineer’s specs.
  • Plumber and electrician to install services including downlighter boxes, etc.
  • Ref100 Mesh to be placed on top of slab and services material. No electrical down pipes to be sticking through the Mesh.
  • Polystyrene to be placed between the concrete slab and the outside brick walls.
  • Remove all the rubble from the slab and wash any excess material from the slab.
  • The appointed engineer has to inspect the slab before casting can commence.
  • Concrete casting to be done – readymix @ 25mpa to 30mpa pumpmix (as per engineer’s specs).
  • Reinforced beams MUST at all times be casted with a poker vibrator and a needle!!! The concrete needs to grip properly around the reinforcing steel.
  • Small slabs can be casted by making use of a concrete mixer and by using an approved recipe available at our office.
  • Wet the slab every day for at least 5 days after casting for proper curing.
  • Wall on wall brickwork can proceed within 24 hours after casting. All other brickwork on the slab has to be done after the props have been removed.
  • Props to be removed after 14 days.
  • Engineer’s Completion Certificate will be issued after the removal of props and shuttering.
  • Plaster only once props have been removed as the slab has settled. 
 

That's great guys! Level walls wil help us to have level ceilings.






We only need a centre line of adjustable props where the clear spans exceed 5,0m. This also levels the soffits with each other. These props remain in possition for 10 days.



Clean off debris and thoroughly wet the slabs before grouting and the V-joints and casting of concrete topping or screed where specified. A detailed specification is available on request.


Ten days after casting the joints and topping, remove the props and finish the butted joint with Rhinolite and a piece of conduit or use 'Profill' or similar to prevent hairline cracks.


This is easy! No plastering required - tyrolean the ceiling before painting or apply a textured coat of paint to the ceiling.






Slabs may be Rhinolite plastered for a completely smooth soffit if required - specifications are available.